Notícias da empresa sobre Installation Steps for Double Face Cartridge Mechanical Seal
1. Pre-Installation Prep: Clean the shaft, seal cavity, and cartridge; check for shaft runout (≤0.05mm) and surface scratches.
2. Cartridge Mounting: Slide the cartridge onto the shaft, align the seal cavity flange, and hand-tighten bolts evenly.
3. Set Axial Clearance: Rotate the shaft to seat the seal faces, use a feeler gauge to adjust clearance to manufacturer’s specs (typically 0.3-1mm).
4. Lock Position: Tighten flange bolts per torque requirements, then secure the cartridge’s anti-rotation pin.
5. Final Checks: Rotate the shaft manually to ensure smooth operation; verify lubrication/cooling circuit connectivity before startup.